Hackney Council has awarded Wates Construction a contract worth up to £25,073,930 to get its Britannia housing scheme in Hoxton East and Shoreditch back on track after the original builder went into administration.
The contract (£30,088,716 including VAT) covers critical path external envelope works (the outer shell) on the four residential buildings of the Britannia Phase 2b Project. Phase 2b will deliver 51 social rent homes, earmarked for Colville Estate households whose homes are being demolished, and 30 shared ownership homes.
The Cabinet Procurement and Insourcing Committee approved it on 2 November 2026 as part of a recovery plan following the administration of main contractor Ardmore Construction Group Limited on 11 June 2026. Before Ardmore went under, the works were estimated to be about six to nine months from completion. However, none of the four buildings were watertight, including the two most advanced towers of 25 and 20 storeys.
The council’s initial priority was to make the site safe and secure and to protect the assets already delivered, as far as possible, from damage and warranty invalidation. Wates took over the site on 30 June 2026. The council will seek to recover losses through routes including a 10% performance bond and a parent company guarantee from Ardmore Group Limited.
Wates had already been working with the council under a Pre-Construction Services Agreement to re-procure the works. Its new contract covers completing the design, procurement and installation of the external envelope, continued site management, and asset and plant protection. It also covers vesting of materials and procurement of long lead-in items for a second contract, and procurement of the internals and the landscape and external works packages.
That second contract, for the remaining internal and landscape works, is expected to go before a future committee meeting, with an award estimated for spring 2027. Its value has not yet been specified.