Haringey’s cabinet has stood by a 40-year deal to heat 202 new council homes through the Energetik district heat network. Councillors had raised concerns about the company’s finances, its possible sale, and its continued reliance on gas.

At a meeting on 13 November 2026, the cabinet confirmed its decision of 20 October 2026 to award heat connection and supply agreements for the Selby Urban Village development. The value of the deal was contained in an exempt report.

Councillor Ibrahim Ali led a call-in of the original decision to the Overview and Scrutiny Committee. Councillors Sue Jameson, Seema Chandwani, Emily Arkell and Dana Carlin also signed it. The committee raised concerns about Energetik’s financial stability, its possible sale, and the timeline for providing low-carbon heat.

The committee recommended that the Cabinet reconsider the decision with more information on the financial risks, the changed policy context and the potential sale. It also recommended that future Cabinet reports put the public interest first and use exempt information only as a last resort.

The Cabinet accepted the transparency recommendation. Guidance for report authors on exempt information will be refreshed and circulated, and training workshops will be held for managers.

Concerns over Energetik’s finances

Energetik is owned by Enfield Council, which is its sole shareholder. The company has secured £92m in low-cost loans from central government.

A recent report to Enfield Council highlighted Energetik’s liquidity pressures and its reliance on gaining more customers, after slower progress than planned in expanding the network. The report said Enfield will need to keep monitoring Energetik’s liquidity position, and that the company could need further working capital support during 2026/27 if more risks materialise.

In response to the call-in, officers said Haringey’s contracts with Energetik would remain enforceable whoever owns the company.

Gas until 2029 or later

The Energetik network is currently supplied by gas-fired boilers. It is due to switch to low-carbon heat from the North London Waste Authority’s Energy Recovery Facility at Edmonton Eco Park. The original Cabinet report expected this by July 2029. That means the first tenants are expected to move in while their homes are still heated by gas.

The call-in said the proposal was not in line with the council’s net-zero commitments, and that the switch to low-carbon heat was “liable to further delays”.

The Overview and Scrutiny Committee noted that published North London Waste Authority papers suggested the Edmonton facility’s completion could slip from 2029 to 2032. Officers said that while a 2032 date had been discussed in negotiations, a revised, non-binding date of 29 December 2029 had been agreed.

Officers said Energetik, not residents, would carry the risk of any delay. The committee heard that any extra costs from delays to decarbonisation, or from using gas instead of lower-carbon sources, would be paid by the supplier rather than passed on to residents through higher unit prices. Officers believe the safeguards negotiated in the contract are enough to manage the risk of delay, whenever the Edmonton facility is finished.

What tenants will pay

Residents will pay a fixed availability charge, which works like a standing charge, plus a consumption charge based on how much heat they use. The availability charge will rise each year in line with the Consumer Price Index (CPI). The consumption charge is linked to the retail gas element of CPI.

Independent advisers benchmarked the costs against alternatives. The Overview and Scrutiny Committee report said they found Energetik’s proposed costs “broadly comparable to, and in some cases slightly lower than” other options for consumers. Officers said the deal was “broadly consistent if not better than” on-site air source heat pumps. Tariffs were also benchmarked against other heat networks through the Heat Trust, and Energetik has committed to charging Selby Urban Village residents the same tariffs as its customers in Enfield.

Council reports say Energetik will be fully regulated by Ofgem from January 2027. Officers said this would bring consumer protections comparable to other energy markets. Charges will have to be fair and transparent, and the rules will cover dispute resolution and supplier-of-last-resort arrangements. Ofgem regulation will not impose price caps.

Diagram illustrating the heat supply arrangements for the Selby Urban Village, differentiating between Energetik's responsibilities and those of the resident or landlord.
Diagram illustrating the heat supply arrangements for the Selby Urban Village, differentiating between Energetik's responsibilities and those of the resident or landlord.Source: Cabinet papers, 13 November 2026

The development

Selby Urban Village will provide 202 new council-rent homes, along with community facilities, green spaces and sports areas. The council says the scheme will bring sustainable, long-term benefits to residents in an area of significant deprivation, and that reaffirming the deal means it can be delivered on time.

The development’s energy strategy requires it to connect to a district heat network, in line with the Greater London Authority’s energy hierarchy and planning obligations.

The agreements include Heat Connection Agreements and a Framework Supply Agreement with Lee Valley Heat Network Operating Company Limited, which trades as Energetik. They cover installing the heat network infrastructure and the ongoing supply of heat to homes, businesses and community facilities in the development.

Other options were considered, including connecting to a different district heat network or building on-site energy centres. These were ruled out on cost and practical grounds. Connecting to other networks would have meant laying pipework over long distances.