Richmond’s 12 libraries could be handed to an outside organisation to run, as the council looks to save £500,000 a year. But officers say bidders will not be asked to close libraries or cut opening hours.

The council’s Environment, Sustainability, Culture and Sports Committee agreed on 18 November 2026 to test the market for new ways of managing and running the service. The saving would be about 11% of the libraries’ £4.43m budget.

The council says the library service performs well but is relatively expensive, costing £25 per resident compared with a London median of £16. The higher cost is mainly due to its large estate of ageing buildings, some of them listed. Some were not originally designed as permanent libraries and lack the flexible space modern services need.

Matthew Eadie, Director of Culture and Leisure, said the council would not be asking providers to look at “rationalisation of buildings, opening hours and things like that”. He said: “It would be to deliver the service up to the standards that we’re already delivering.”

The service has just over 100 staff.

As well as testing the market, officers will look at making better use of library buildings, including flexible access, sharing buildings and moving services in together. The report says the council wants to check “whether we have the right buildings in the right places”. The aim is to put the service on a sound financial footing while protecting its quality. The council will set minimum service standards, which any bid must meet. Bidders will be encouraged to offer added value, particularly financial.

The savings depend on a charity running the libraries. Mr Eadie said that, based on the council’s library buildings alone, a charity would get business rates relief of “about £220,000 or £230,000”. Charities may also be able to attract extra funding and achieve economies of scale. However, the council identified a risk that a provider could go out of business.

The council is also exploring running the process jointly with Wandsworth Council. It expects this would attract more interest from providers, need fewer staff to run the tender and produce bigger savings.

‘All the important decisions’

Under an indicative timetable, the tender would be launched in April, with possible check-ins with the committee in January, February and April.

Councillors insisted that key decisions on service standards and the overall approach must come back to them before any contract is awarded. Councillor Dr James Chard, who said he works in procurement, warned that the key choices would be made at the very start.

“By the time you’ve produced your specification and procurement documents, you are set down along the road, and all you are deciding is which provider is best able to meet your requirements,” he said. “It might well be that this committee has different views on what the minimum standards are, how many libraries should be provided, those kind of issues, and those parameters are going to be in the procurement documents. All the important decisions are taken at point one, and then it’s just assessment and appointment.”

The committee amended the recommendations so that officers must report back for a decision on next steps once initial talks with potential providers are complete, expected in spring 2027.

In the meantime, the council has proposed an immediate 10% cut to the library book fund, worth £43,000. The fund pays for all the physical and electronic books and resources people can borrow across the 12 libraries.