Hospital bosses cannot guarantee that maternity services will return to St Helier Hospital if they are moved out while contaminated water pipes are replaced, councillors have been told.
Epsom and St Helier's trust board will choose its preferred option for the hospital's women's health block, known as E block, on 3 December. Routine testing in 2024 found legionella and pseudomonas bacteria in the building's corroded water system.
Mat Shaw, group chief executive of St George's, Epsom and St Helier hospitals, told Merton Council's Healthier Communities and Older People scrutiny panel on Tuesday 24 November 2026 that any move would be temporary. But he said he could not give a 100%
guarantee that services would go back.
Major building works could uncover further problems, he said. And the long-term future of maternity services was a decision for the NHS integrated care board, which may review them as birth rates fall. I can't promise something which is outside of my control,
he said.

Two options
Two options have been shortlisted from an original 10. The first is a phased hybrid
approach, replacing the pipework one floor at a time while services move around the building, at an estimated cost of £47m. The second would disperse maternity and neonatal care to other hospitals for about £37.89m, with around 700 births a year going to Epsom, 700 to St George's and 300 to 400 to Croydon, which would each need building work to take them. St Helier currently has about 1,800 births a year.
Under either option, services and staff would not be affected until about December 2028. The building would be fully back in use by February 2030 under dispersal, or July 2030 under the hybrid approach.
Michael Pantlin, the group's deputy chief executive, said: The second fact is we can't afford either option.
No funding has yet been approved, and the trust will have to bid to a national NHS fund for failing buildings once it chooses its preferred option. Water testing alone is costing the trust more than £3m a year.
Doing nothing, or replacing the pipes with all services still in the building, were both ruled out as too risky. Mr Shaw said carrying out building works around patients risked spreading aspergillosis, a fungus in building dust that can be fatal to newborn babies and people with weakened immune systems. The assisted conception unit will get a new permanent home on the St Helier site.
The risks of each option were set out in board papers. The phased approach raises infection control concerns from construction close to clinical areas. Dispersal raises concerns about travel for women and families, women's choice, staff willing to move between hospitals, and staffing arrangements across trusts.

Emergency risk
Mr Shaw said the trust's biggest fear was a sudden rise in bacteria levels that forced services out of the building within days
. The risk is currently low but grows over time. A detailed emergency plan has not yet been finalised, and Michelle Cudjoe, group chief midwifery officer, said such a move would be a major incident for south west London.
'Temporary' questioned
After the board's decision, the trust plans six to eight weeks of public engagement rather than a formal consultation, which it says is not legally required for a temporary move made for health and safety reasons.
One councillor said a planned move four years away was not an emergency, and questioned how services could be described as temporary when their return could not be guaranteed. Cllr Billy Hayes said it felt like death by a thousand cuts
. Panel chair Cllr Agatha Akyigyina said people had lost faith in consultations because their views were ignored.
Cllr Peter McCabe, Merton's cabinet member for health and social care, said St Helier served some of the borough's most deprived communities and that moving services away would widen health inequalities. He said 220 staff in the building had written to the board saying they preferred to stay on site.
The trust said it had completed equality, quality, workforce and financial impact assessments, including travel times and the effect on women from deprived and ethnic minority communities.

Ageing buildings
The trust has spent £60m in recent years maintaining its ageing buildings, but problems remain. Thirteen beds in the reablement unit for frail older patients closed after cracks appeared in the walls, and repeated lift failures have affected children's services. A new hospital in Sutton has been delayed until at least 2037. Meanwhile, the trust has secured up to £57m to expand St Helier's emergency department, with a temporary 12-bed unit due to open before Christmas.