Bexley Council's housing company, BexleyCo, plans to build 410 more homes across eight sites, but high costs and a tough market have trimmed the money it expects to make.
The company's 2026 business plan, approved at the council's Public Cabinet on 25 November 2026, adds to the 120 homes it has already completed. It forecasts pre-tax profits of about £19.8 million and gross returns to the council of £38.9 million, about £2 million lower than last year's plan. The plan blames higher construction costs left over from past inflation, a difficult market for first-time buyers and later completion dates.
Work is under way at Bursted Woods in Barnehurst, where 121 homes, including 18 affordable homes and the conversion of the listed former maternity hospital, will be completed in four phases between November 2027 and November 2029. A further phase of about 49 homes, including supported living, will follow on the adjacent site. Lesney Park in Erith is consented for 17 houses and eight supported living flats for affordable rent, with completion due in March 2028.

Erith High Street, the former Post Office site, has planning permission for 33 flats and two small shops, but the company is still weighing up how to deliver it after construction tenders came in higher than expected. Burr Farm in Bexleyheath, planned for 70 family homes around a new village green, is due at planning committee in February, with affordable homes increased from six to ten. An application is ready for Belvedere Family Centre, a 13-storey block of 86 flats with commercial space that could house a new GP surgery.
At Sidcup Manor House, the manor will be sold for use as a day nursery, while BexleyCo converts the listed coach house and builds eight new family homes. At Crayford Manor House, about 17 homes are planned, but surveys have been held up by serious fly-tipping on the site. Final numbers on these five sites depend on design and planning consent.

BexleyCo says its Local First
policy will give local buyers the first chance to buy its homes.
The plan admits the pressures are already showing. Only eight of the 30 flats at West Street in Erith have sold since completion in April 2025, so unsold homes are now being rented out. A Labour councillor told the meeting the scheme had taken a well-used green space without providing affordable homes or a dividend. Council leader David Leaf said the council had sought an affordable housing partner but the GLA turned down the grant application, and market conditions had since worsened. At the former Sidcup Library, completed in November 2025, 21 of 32 flats have sold. Opposition leader Councillor Stefano Borella called it disgraceful
that the scheme included no affordable housing. Cllr Leaf replied that, like any developer, BexleyCo had to focus on viability.

The company's future is also under review. The council plans a review of its assets that will include BexleyCo, so this year's plan focuses only on the sites with the clearest viability. BexleyCo's longer-term ambition to deliver around 1,000 homes will be revisited once the review is complete. Cllr Leaf said he could not yet give a timescale.
The council's funding for the company, in loans and equity, is forecast to peak at about £72.4 million in 2029-30 and be fully repaid by 2032-33. Further dividends to the council are expected from 2028-29.