The City of London is initiating a Section 278 road project for 1 Undershaft, with design work starting in November 2026.

The Streets and Walkways Sub (Planning and Transportation) Committee approved the initiation of a Section 278 project for 1 Undershaft in November 2026. This project involves constructing a new road in Undershaft and reconstructing pavements and roads on Leadenhall Street and St Mary Axe.

The project, which is fully funded by the developer, has an initial allocation of £280,000 for its evaluation and design phase, aiming to progress to Gateway 3. Design work, including commissioning surveys, is expected to begin in November 2026, with a Section 278 / s38 agreement anticipated by Summer 2028.

Key facts

  1. The Streets and Walkways Sub (Planning and Transportation) Committee approved the project's initiation in November 2026. Source
  2. The project involves constructing a new road in Undershaft and reconstructing pavements and roads. Source
  3. The project is fully funded by the developer. Source
  4. An initial allocation of £280,000 was made for the evaluation and design phase. Source
  5. A Section 278 / s38 agreement with the developer is anticipated by Summer 2028. Source
About this summary

This summary was written automatically from our published stories and the council meeting records they draw on. It describes what councils have discussed and decided; it does not take a view on any decision. Each key fact links to the story it comes from. Updated 2 November 2026. Spotted a mistake? Email community@opencouncil.network.

Latest stories

  1. New road project planned for 1 Undershaft A significant road project is set to commence at 1 Undershaft. The Streets and Walkways Sub (Planning and Transportation) Committee has approved the initiation of a Section 278... City of London 2 November 2026