Alexandra Palace is planning to replace its Panorama Room in a £3.5m project. Funded by a loan from Haringey Council, it aims to finish it in time for the World Darts Championship, which starts in December 2027.
The existing structure, in use since 2003, has reached the end of its working life and is no longer considered fit for purpose. The new building is designed to be more sustainable and more accessible for disabled visitors, structurally stronger, and cheaper to maintain. It is also intended to support the Trust’s commercial income.
The Panorama Room is described as “an intrinsic part of the event offer”. It is often sold as part of key events at the palace, including the World Darts Championship, the Knitting and Stitching Show and snooker.
The plans were set out in a report to the Alexandra Park and Palace Board on 29 October 2026.

StarLive was appointed as main contractor after a competitive tender in autumn 2025, and the design is being developed. The new single-storey building will sit on a similar footprint to the existing one and will have improved facilities for events, catering and visitors. These will include toilets, a bar, a cloakroom, a kitchen, storage, a plant room, a tech and AV office, and dressing rooms.
The Trust is preparing to apply for a loan from Haringey Council, which is due to be discussed at the council’s cabinet meeting on 8 December 2026. Haringey Council is the sole trustee of the Alexandra Park and Palace Charitable Trust, and its grant provides 24% of the Trust’s income.
The report says the loan repayments “will be supported through increased revenue generated by the improved facilities and enhanced delivery of events”. It lists the risk that the charity may be unable to make the repayments, and says forecasts have been prepared and discussions with the council are continuing. The full loan terms have not yet been agreed.
The project is being managed through a Planning Performance Agreement with Haringey Council. Applications for planning permission and listed building consent were due to be submitted on 6 October 2026.
If permission and funding are secured, construction is expected to take about six months, with completion in October 2027. The report says the work “will be closely coordinated with the events programme to ensure impact is minimal”.

The main risks include getting planning approval, construction costs, disruption to events, and unexpected work in the palace’s historic basements. These are being managed through a risk register for the whole project. The report warns that work in the basements could uncover “additional work and complexities”. The structural engineer, contractor and architect are working closely together, and “a healthy contingency for the basement works is being discussed”. The report does not say whether this is included in the £3.5m.