Romford is set to get the tallest building in Havering after councillors approved plans to rebuild the edges of the Liberty Shopping Centre with up to 900 homes.
Havering Council's planning committee voted 4-1 on 26 November 2026 to approve the plans. The application is a hybrid: full permission for the first phases, on Western Road and Market Place, and outline permission for later phases.
The centrepiece is a 23-storey block on Western Road. It exceeds the heights recommended in the Romford Masterplan, but officers said it would act as a landmark and help people find their way. They said its impact was softened by setting it back 25 metres from the street, behind lower blocks.
All the homes will be built to rent and will be one, two and three-bedroom flats. The scheme must stay as build-to-rent for at least 15 years.
Although the council's viability review found the scheme would run at a loss, the developers have committed to some affordable housing, let at discounted market rent:
- At least 5% of homes in the first and second phases, and 10% in the third, measured by habitable room
- Across the 742 homes in the illustrative scheme, that would mean 43 discounted homes, or 6% overall.
Early, mid and late reviews could increase the number.
Concerns
Historic England, the council's own heritage officer and Romford Civic Society all raised concerns about harm to the Romford Conservation Area. They objected in particular to the six-storey blocks proposed for Market Place. Historic England recommended capping them at four and five storeys. Officers advised that the benefits outweighed the harm, including much-needed homes, affordable housing, an improved public realm, and a boost to the town centre.
The plans keep the heart of the shopping centre open while replacing what developer Hub called its tired edges
with new ground-floor units for shops, restaurants, cafes and independent businesses, under a new glass roof. The applicants said the commercial space being redeveloped, including Lambourne House, is largely vacant and in places near derelict.
There will be a net loss of 11,649 square metres of shop and commercial floorspace, less than the 13,200 square metres currently empty. About 23,000 of the existing 37,000 square metres of ground-floor retail will be kept.
New food and drink quarter
Swan Walk will be widened into a new food and drink quarter with a better link to Market Place. There will also be a new public square off Western Road, by a new entrance to the centre, a new street off South Street, and 2,700 square metres of rooftop workspace, called Maker's Yard, which the public will be able to use.
A condition requires details of opening hours for the main atrium, which could keep routes through the centre open later and boost the evening economy.
The outline phases are capped at 408 homes and 712 square metres of commercial, community and town centre uses. Those uses could include shops, food and drink outlets and a health centre, as well as pubs, wine bars, hot food takeaways and a laundrette.
The scheme is car-free apart from blue badge spaces, all with electric vehicle charging, and residents will be barred from parking permits. The site has the best possible public transport access rating, PTAL 6a to 6b. Council highways officers raised concerns about the layout, accessibility and security of residential cycle storage, and noted there are no meaningful cycle route improvements.
Conditions require a Parking Design and Management Plan, Stage 1 and Stage 2 road safety audits, and a final Delivery and Servicing Plan.
Work on the detailed phases must start within three years. Details of the first outline phase must be submitted within three years, and all remaining details within seven. Each phase must then start within two years of its details being approved.
The developers' legal agreement includes:
- Over £1.7 million for schools, from the first phases alone
- Up to £1.36 million for health services if no on-site health facility is needed
- About £972,000 to offset carbon emissions
- £250,000 for step-free access at Romford Station
- Up to £900,000 for the ring road, public realm, highways and Market Place
- Facilities for bus drivers.
Officers acknowledged a noticeable loss of daylight to flats in Halyards Court opposite. They judged it acceptable in a dense town centre, given the need to make the best use of brownfield land. The scheme also includes accessible homes and play space that meet London Plan standards.
The developers are Hub and Redigal, which bought the centre in 2022. Hub said Redigal has since spent £22.8 million upgrading the centre, modernising shops and bringing in new brands.